Electric transmission towers at sunset. Source: Matthew Henry, via Unsplash. License: Unsplash License.
Quick Answer: Duke Energy Florida, the St. Petersburg-based utility that serves Pinellas and Pasco counties, earned $424 million in segment income in the third quarter of 2026, up 6.5% from $398 million a year earlier, even though operating revenue fell 13.4% to $1.867 billion. In early November, Florida regulators approved lower bills for 2027 and rejected the company’s data center tariff, and Duke filed plans for four more solar sites.
Duke Energy Florida is headquartered in St. Petersburg and serves about 2 million customers. Its third-quarter numbers, released by parent company Duke Energy Corp. on November 5, 2026, show higher profit and steady customer growth. The same weeks brought a rate cut for 2027, a fresh solar filing and a setback before the Florida Public Service Commission (PSC) on data centers.
How much did Duke Energy Florida earn in the third quarter of 2026?
Duke Energy Florida reported segment income of $424 million for the three months ended September 30, 2026, compared with $398 million in the third quarter of 2025. That is an increase of $26 million, or 6.5%. For the first nine months of 2026, Florida segment income reached $1.040 billion, up 5.6% from $985 million in the same period of 2025.
Operating revenue moved the other way. Third-quarter revenue was $1.867 billion, down $290 million, or 13.4%, from $2.157 billion. Nine-month revenue fell 6.1% to $5.154 billion. Operating income still rose 6.3% to $628 million in the quarter. The line-item comparison below comes from the consolidating segment tables in Duke Energy’s third-quarter 2026 and 2025 earnings releases.
| Duke Energy Florida ($ millions) | Q3 2026 | Q3 2025 | Change | 9 months 2026 | 9 months 2025 |
|---|---|---|---|---|---|
| Operating revenues | 1,867 | 2,157 | -13.4% | 5,154 | 5,486 |
| Fuel and purchased power | 518 | 546 | -5.1% | 1,413 | 1,378 |
| Operation, maintenance and other | 242 | 577 | -58.1% | 792 | 1,354 |
| Depreciation and amortization | 341 | 297 | +14.8% | 943 | 861 |
| Operating income | 628 | 591 | +6.3% | 1,621 | 1,506 |
| Interest expense | 135 | 118 | +14.4% | 389 | 352 |
| Income tax expense | 89 | 97 | -8.2% | 245 | 238 |
| Segment income | 424 | 398 | +6.5% | 1,040 | 985 |
Why did revenue fall while profit rose?
The biggest swing was in operation, maintenance and other expense, which dropped from $577 million to $242 million in the quarter. The earnings release does not itemize that change. The timing lines up with the end of the interim storm restoration charge for Hurricanes Debby, Helene and Milton. The PSC approved that charge in February 2025, and it added about $33 per 1,000 kilowatt-hours (kWh) to residential bills starting in March 2025. Duke Energy Florida stopped collecting it at the end of January 2026, so the third quarter of 2025 included a full quarter of storm-cost billing and the third quarter of 2026 included none. Storm-cost recovery revenue is largely offset by expense, which would explain why both fell without denting profit.
What drove profit higher was the base business. In its earnings materials, Duke Energy credited “DEF Year 2 rates, effective January 2026” with adding 3 cents per share to the quarter and 8 cents per share year to date. That is the second step of the multiyear rate agreement the PSC approved in 2024. Part of the gain went to a larger asset base: depreciation rose 14.8% and interest expense rose 14.4%.
How fast is Duke Energy Florida’s customer base growing?
Duke Energy Florida averaged 2,069,604 retail customers in the third quarter, up 28,932, or 1.4%, from a year earlier. Residential customers grew faster than any other class in absolute terms, and residential electricity sales rose 4.2%.
| Metric (Q3) | 2026 | 2025 | Change |
|---|---|---|---|
| Average residential customers | 1,849,168 | 1,822,296 | +1.5% |
| Average commercial customers | 215,393 | 213,293 | +1.0% |
| Average industrial customers | 1,591 | 1,564 | +1.7% |
| Total average retail customers | 2,069,604 | 2,040,672 | +1.4% |
| Residential sales (GWh) | 7,394 | 7,093 | +4.2% |
| Commercial sales (GWh) | 4,767 | 4,701 | +1.4% |
| Industrial sales (GWh) | 833 | 823 | +1.2% |
| Renewable generation (GWh) | 1,117 | 969 | +15.3% |
Total Florida retail sales rose 1.4% in the quarter and 1.5% on a weather-normalized basis. Weather made little difference: Florida cooling degree days were 1,578, compared with 1,579 a year earlier. Through nine months, retail sales were up 1.5%, or 0.9% after adjusting for weather.
Natural gas and oil produced 11,122 of the 13,418 gigawatt-hours (GWh) Duke Energy Florida generated in the quarter. Owned summer capacity was 12,004 megawatts (MW), up from 10,980 MW a year earlier.
How did parent Duke Energy perform overall?
Duke Energy Corp., based in Charlotte, North Carolina, reported third-quarter 2026 earnings of $1.99 per share on both a GAAP and an adjusted basis, compared with $1.81 a year earlier. Year-to-date adjusted earnings were $5.35 per share, up from $4.81. The company narrowed its 2026 adjusted earnings guidance to $6.70 to $6.80 per share and kept its long-term target of 5% to 7% annual adjusted EPS growth through 2030.
Its Electric Utilities and Infrastructure segment, which includes Duke Energy Florida, earned $1.817 billion in the quarter, up from $1.658 billion. Chief Executive Harry Sideris said in the release: “We delivered strong results through the first three quarters of the year, reflecting disciplined execution.”
What will Duke Energy Florida customers pay in 2027?
On November 3, 2026, Duke Energy Florida announced that the PSC had approved its request to lower rates in 2027. According to the company:
- A typical residential customer using 1,000 kWh a month will pay $33 less in January 2027 than in January 2026.
- From December 2026 to January 2027, that same residential bill drops by about $0.95.
- Commercial and industrial bills fall between 0.9% and 3.8% from December to January, depending on the customer.
- Starting in March 2027, residential customers get an additional temporary reduction of $10 per 1,000 kWh. The company applies it each year from March through November, when usage tends to be highest.
The company credited what it called an “innovative tax strategy” with letting it avoid a base rate increase that had been scheduled for 2027. In its September 3 filing announcement, datelined St. Petersburg, Duke Energy Florida said it was avoiding a 2% base rate increase that the PSC set in 2024, a move it said would bring forward $50 million in customer savings for 2027.
What happened to the hurricane storm charge?
WUSF reported that the storm recovery effort totaled $1.1 billion and that the charge came off bills after January 2026. That cut residential bills by about $33 per 1,000 kWh in February, with another $11 reduction in March. In May 2026, the PSC authorized a $90.5 million refund after the utility collected about $1.006 billion in storm charges against actual costs of about $915.3 million for Debby, Helene and Milton. The refund was returned through a temporary cut in the residential fuel rate from 4.414 to 3.852 cents per kWh for billing cycles from June through September 2026.
What is Duke Energy Florida building next?
On November 10, 2026, Duke Energy Florida said it had filed plans with the PSC for four new solar sites totaling about 300 MW. All four are tentatively scheduled to be in service by June 2028:
- Nova Renewable Energy Center, Orange County: construction January 2027, completion February 2028.
- Bull Creek Renewable Energy Center, Orange County: construction March 2027, completion April 2028.
- Hogeye Renewable Energy Center, Sumter County: construction May 2027, completion May 2028.
- Wewahootee Renewable Energy Center, Orange County: construction May 2027, completion June 2028.
The company estimates that each site will save about $250 million in displaced fuel costs over a roughly 30-year life, about $1 billion in total. It expects production tax credits to return about $75 million a year to customers. Duke Energy Florida already operates 25 solar sites totaling 1,850 MW.
What has changed at the Bartow plant in St. Petersburg?
Closer to home, WUSF reported in January 2026 that Duke Energy Florida had finished efficiency upgrades at the Bartow Power Plant on Weedon Island Drive in St. Petersburg. The work added 88 MW of output by replacing key turbine components with more efficient parts. Upgrades at four Florida gas plants added 330 MW in total, for an investment of about $161 million. The company says they produce $340 million in annual fuel savings, which it puts at about $10 off monthly bills, and work at the remaining plants is expected to finish by early 2027.
Why did regulators reject Duke’s data center tariff?
The quarter’s main regulatory setback involved large electricity users. Senate Bill 484, signed in May 2026 and in effect since July 1, requires utilities to make data centers and other large loads pay the full cost of their service. Utility Dive reported that Duke Energy Florida was the first investor-owned utility to file a compliance proposal. Its plan included a 20-year minimum service term and a requirement that large-load applicants pay the estimated cost of extending service up front.
Bay News 9 reported on November 10 that the PSC unanimously rejected the proposal, saying it did not meet SB 484, and that Duke Energy Florida could file a new petition. Tampa Electric’s own proposal was still awaiting review. For Pinellas and Pasco businesses, the rules for serving large new loads are still unsettled.
What does Brookfield’s investment mean for Duke Energy Florida?
In August 2025, Duke Energy agreed to sell Brookfield a 19.7% indirect, non-controlling interest in Duke Energy Florida for $6 billion in cash. Duke kept 80.3% and remains the operator. The announcement raised Duke Energy Florida’s five-year capital plan by $4 billion, to more than $16 billion through 2029, for grid modernization, resiliency and generation. That ownership change appears in the third-quarter numbers. Duke cited “minority interest impacts” of 7 cents per share in the quarter, and net income attributable to noncontrolling interests rose to $85 million from $33 million.
Duke Energy Florida at a glance
| Item | Detail |
|---|---|
| Headquarters | St. Petersburg, Florida |
| Parent | Duke Energy Corp. (NYSE: DUK), Charlotte, N.C.; Brookfield holds a minority stake |
| State president | Melissa Seixas |
| Customers | About 2 million in 35 counties, including Pinellas and Pasco |
| Owned capacity | 12,500 MW (company description); 12,004 MW summer capacity in Q3 earnings data |
| Q3 2026 segment income | $424 million (+6.5%) |
| Solar fleet | 25 sites, 1,850 MW; four more (about 300 MW) proposed |
| 2027 residential bill | $33 lower than January 2026 per 1,000 kWh |
Brian’s Take
The number I keep coming back to is the gap between revenue and profit. Revenue fell 13% and segment income still rose 6.5%. That tells me the storm-cost collections were inflating last year’s top line, and the business underneath is a steady, regulated earner growing with its customer count. Nearly 29,000 net new customers in a year, mostly households, is the kind of slow, compounding growth Tampa Bay businesses can plan around.
For Pinellas and Pasco employers, the bill news is real but worth reading carefully. A $33 drop compared with January 2026 mostly reflects the storm charge coming off. The December-to-January change is under a dollar for a typical household, and 0.9% to 3.8% for commercial accounts. Helpful, but not a new era of cheap power, and rising depreciation and interest expense show the cost of the build-out is still climbing.
The data center ruling is the one I would watch. Florida now has a law saying big loads must pay their own way, and regulators just showed they will enforce it. I think that protects existing ratepayers, including small businesses. It also means anyone hoping to land a large power user in this region will be waiting on a rulebook that is not finished yet.
Frequently Asked Questions
How much did Duke Energy Florida earn in Q3 2026?
Segment income was $424 million for the quarter ended September 30, 2026, up from $398 million a year earlier. Operating revenue was $1.867 billion, down from $2.157 billion.
Will Duke Energy Florida bills go down in 2027?
Yes. With PSC approval, a typical residential bill for 1,000 kWh will be $33 lower in January 2027 than in January 2026, and about $0.95 lower than in December 2026. A seasonal $10 reduction applies from March through November.
Is the hurricane storm charge still on bills?
No. Duke Energy Florida stopped collecting the 2024 hurricane storm charge at the end of January 2026. A $90.5 million over-collection was refunded through lower fuel charges from June through September 2026.
What new solar projects has Duke Energy Florida proposed?
It has filed plans for four sites totaling about 300 MW: Nova, Bull Creek and Wewahootee in Orange County and Hogeye in Sumter County. All four are targeted for service by June 2028.
What happened to Duke’s data center tariff?
The PSC unanimously rejected it in November 2026, finding that it did not meet the requirements of Senate Bill 484. Duke Energy Florida can file a new proposal.
Sources and Further Reading
- Duke Energy Reports Third Quarter 2026 Financial Results, Form 8-K earnings release, Duke Energy Corp. (U.S. Securities and Exchange Commission)
- Duke Energy Reports Third Quarter 2025 Financial Results, Form 8-K earnings release, Duke Energy Corp. (U.S. Securities and Exchange Commission)
- Duke Energy Florida customers to see lower rates in 2027, Duke Energy Florida (PR Newswire)
- Duke Energy Florida requests to lower rates in 2027, Duke Energy Florida (PR Newswire)
- Duke Energy Florida plans 4 new solar energy sites to deliver $1B in customer savings, Duke Energy Florida (PR Newswire)
- Duke Energy partners with Brookfield to secure investment in Duke Energy Florida, expands capital plan to $87 billion, Duke Energy Corp.
- Duke Energy Florida ends storm recovery charge early, WUSF Public Media
- Duke Energy Florida customers to receive $90.5 million refund after storm cost over-collection, WTXL
- Duke completes efficiency upgrades at St. Pete plant, WUSF Public Media
- Florida Public Service Commission rejected Duke Energy Florida’s proposal for handling cost tied to data centers, Bay News 9
- Duke Energy Florida large load tariff hearing coverage, Utility Dive
- Duke Energy Florida 2026 Hurricane Preparedness Workshop Presentation, Florida Public Service Commission